An AHU filter-change work order closed with the comment 'done' tells an inspector nothing about the room it serves.
In a GMP plant the work order is the record that the equipment went back into service in its qualified state. A CMMS allows it to be closed with one click. The procedure behind it should ask for more.
Before closure, four things belong on the record:
- As-found and as-left. The filter pressure drop before and after, the damper position, the instrument reading before adjustment. An as-found value outside tolerance on a calibrated instrument opens an impact assessment on everything it measured since its last calibration.
- Parts used, by part number and batch where it matters. A like-for-like part stays in maintenance. A different filter class, gasket material or sensor range is a change, and belongs in change control before it is fitted.
- Sign-off by the technician who did the work, then review by someone accountable for the system. For GMP-critical equipment, QA's part in that review should be written down, not assumed.
- The deviation or change control number, if either was raised, so the trail can be followed in both directions.
Annex 11 then expects the CMMS to keep an audit trail of who changed those fields and when.
Humiley runs a GMP CMMS built for life-science maintenance.
What does your CMMS require before a work order can close?