The supplier file holds one page, an ISO 9001 certificate, and the inspector asks what you assessed.
The certificate shows that a certification body audited the supplier's quality management system, for the activities and sites named in its scope. It does not say that the AHU, the control panel or the calibration service you bought meets your requirement. Read the scope line: sometimes it is a sales office, or a factory other than the one building your unit.
Qualification looks at the thing you buy. For equipment, EU GMP Annex 15 (2015) says the specification should be defined in a URS and/or a functional specification and that, prior to installation, equipment should be confirmed to comply with it at the vendor site, if applicable. For outsourced GMP activities, Chapter 7 makes the contract giver responsible for assessing the legality, suitability and competence of the contract acceptor. For computerized systems, the 2011 text of Annex 11 (clause 3) says the need for an audit should be based on a risk assessment.
So the depth follows the risk. A questionnaire and the certificate may be enough for a standard part. A custom AHU for a Grade B suite deserves an audit and hold points in the factory.
Our equipment is built by qualified manufacturing partners under Humiley engineering control and EU-GMP-aligned QC, and every unit is FAT-tested and witnessed.
What is in your supplier file besides the certificate?