What to bring to a factory acceptance test

  • Manufacturing & Distribution
  • 1 min read

A FAT witness who arrives without the approved specification can watch the vendor's test, but cannot check it.

The factory tests that catch problems in the factory, where they are cheap to fix, tend to share one thing: the client's witness came prepared. What to bring:

  1. The approved drawings and datasheets, at the revision the order was placed against. The tender set is not good enough.
  2. The approved FAT protocol, with acceptance criteria written as numbers, and a copy you can mark up.
  3. The specification clause list, so each test can be traced to the requirement it proves.
  4. The list of test instruments you expect to see, to check their calibration certificates on the day.
  5. An agreed punch-list format and someone with the authority to sign it, or to say the unit does not ship yet.

The fifth matters most. A punch list without an owner turns into an email thread, and the unit ships with the thread still open. On site that thread becomes a delay in IQ.

At Humiley every unit is FAT-tested and witnessed against the approved specification, and the equipment file (material certificates, FAT report, O&M, spares) is compiled during production, so IQ starts from a complete record. Manufacturing coordination and FAT run from our engineering office in Ho Chi Minh City.

Tell us what your witnesses bring that is missing from this list.

Related

More on this subject

A work order closed with ticks holds no data. Rewrite each 'check' as a named measurement with its acceptable range and the action to take outside it, and record the as-found value before any adjustment. Start with the assets the criticality assessment ranks highest. The as-found figures become the trend.