AHU warranty: from commissioning or from delivery

  • Engineering Solution & Consultancy
  • 1 min read

An AHU delivered in March and started in November has spent eight months of an 18-months-from-delivery warranty before moving air.

Equipment warranties are often written as 12 months from commissioning or 18 months from delivery, whichever ends first. The clause looks generous. When the building is late, it is not. In that example the 18 months run out the following September, ten months after start-up, two months short of the 12 the owner thought they had.

Storage adds a second condition. Warranties usually hold only if the unit was stored as the manufacturer instructed: covered, dry, fans turned by hand at set intervals, openings sealed. On a site in the wet season that is work somebody has to do and record. Without the log, the first bearing failure becomes an argument about storage instead of a warranty claim.

Three things to settle before the purchase order:

  1. Tie the warranty start to commissioning, or extend the delivery limit to match the program.
  2. Get the storage instructions in writing with the order, and name who carries them out on site.
  3. Agree what happens to the dates if the owner delays start-up.

Every AeroSano unit is FAT-tested and witnessed, and its equipment file is compiled during production. The dates in the warranty clause deserve the same care.