Six weeks after a long-lead item slips, the risk that predicted it is often still in the register, scored as it was at kick-off.
We have sat through plenty of weekly reviews that let that happen. The FMEA spreadsheet goes up on the screen, someone scrolls, the scores stay where they were and the meeting finishes on time.
The fix is to ask the same five questions every week and not leave until each has an answer:
- What is new since last week? New scope, a late vendor drawing, a site condition. If nothing is new, someone is not looking.
- Which scores moved, and why? A severity or occurrence score that never changes is a sign nobody is re-scoring.
- Who owns each open risk? Name a role. A department does not chase actions.
- What is the next action, and when is it due? "Monitor" is not an action unless it names what to watch and the threshold.
- What can we close, and what is the evidence? Closing risks keeps the register short enough to read.
Twenty minutes is usually enough if the register is maintained between meetings.
In our EPCM work the FMEA register is live and reviewed weekly, and the monthly report carries it next to schedule, cost and earned value.