Dust built into a cleanroom during construction takes weeks to clean out at the end.
Some of it never leaves. It sits above the ceiling and in ducts that ran open, and comes down whenever a panel is disturbed. A clean build protocol keeps it from going in. ISO 14644-4:2022 puts a clean build protocol in the construction plan, to minimize contamination during construction. The staging below is one common way to write it; projects cut the stages differently.
- Build the shell and first fix under normal site rules. Do the dirty work now: chasing, coring, grinding, welding.
- Close the envelope: walls, ceiling and floor are in. From here nothing is cut or drilled inside the room. Parts are cut outside, and duct ends stay capped.
- Run the HVAC on temporary filters, with the room under positive pressure. Clean tools only, overshoes, no cardboard or timber.
- Final-clean with gowning and a controlled entry list, repeated until the wipes come back clean.
- Fit the terminal HEPA filters last, once the ductwork has been blown through, and leak-test them in place.
Each stage needs a gate: who inspects, against what, and who signs before the rules tighten. Without it, stage 3 arrives on the program while a late trade is still drilling.
The stricter stages slow every trade, and the contractor will ask who pays for that. Settle it in the tender. In the week before OQ the same argument costs the program.