Clean build protocol: staged rules and a gate before each

  • Project Management Consultancy
  • 1 min read

Dust built into a cleanroom during construction takes weeks to clean out at the end.

Some of it never leaves. It sits above the ceiling and in ducts that ran open, and comes down whenever a panel is disturbed. A clean build protocol keeps it from going in. ISO 14644-4:2022 puts a clean build protocol in the construction plan, to minimize contamination during construction. The staging below is one common way to write it; projects cut the stages differently.

  1. Build the shell and first fix under normal site rules. Do the dirty work now: chasing, coring, grinding, welding.
  2. Close the envelope: walls, ceiling and floor are in. From here nothing is cut or drilled inside the room. Parts are cut outside, and duct ends stay capped.
  3. Run the HVAC on temporary filters, with the room under positive pressure. Clean tools only, overshoes, no cardboard or timber.
  4. Final-clean with gowning and a controlled entry list, repeated until the wipes come back clean.
  5. Fit the terminal HEPA filters last, once the ductwork has been blown through, and leak-test them in place.

Each stage needs a gate: who inspects, against what, and who signs before the rules tighten. Without it, stage 3 arrives on the program while a late trade is still drilling.

The stricter stages slow every trade, and the contractor will ask who pays for that. Settle it in the tender. In the week before OQ the same argument costs the program.

Related

More on this subject

Energy recovery in once-through potent suites

Many potent suites recirculate through safe-change HEPA housings; where the risk assessment rules that out, every cubic metre is tropical outdoor air. Run-around coils recover heat with the airstreams fully separated, wheels open a leakage path, and dedicated fresh-air pre-cooling targets the latent load. Our energy modeling targets a 30% HVAC energy reduction.

InsightRead

Energy savings and the requalification bill

Energy measures that change validated cleanroom conditions go through Annex 15 change control. Classification alone can mean 10 sample locations for a 50 m² room, at rest and in operation, before recovery tests and a CCS update. Price that next to the kWh, or design reduced modes in and qualify them once.

InsightRead

EU GMP Chapter 3 and 21 CFR 211 on HVAC

21 CFR 211.42 and 211.46 and EU GMP Chapter 3 ask for adequate ventilation, air control and filtration, but give no air change rate or pressure differential, and no filter class beyond HEPA for aseptic areas. Those come from Annex 1, FDA's 2004 aseptic guidance, ISO 14644 and the designer's justification, recorded in the design basis.

InsightRead