Skip to content

Manufacturing & Distribution

Write the FAT protocol before the steel is cut

  • Manufacturing & Distribution
  • 1 min read

A FAT protocol that turns up in the week of the FAT is usually written by someone standing next to the finished unit.

It slips because nobody needs it while the drawings are under review. When it is finally written, the acceptance values drift toward what the unit can already do, and nobody checks it against the specification line by line.

Written alongside the drawings, it works differently. Each requirement in the approved specification gets a test, a method, an instrument and an acceptance value: airflow at design pressure, casing leakage, fan speed range, alarm and interlock behaviour. Take the heater interlock. The spec says the heater cuts out on airflow failure. The protocol line says stop the fan, record whether the heater trips, and fail the unit if it stays on. Any requirement that cannot be turned into a line like that goes back to the spec now, while it can still be changed without cutting steel twice.

An early protocol also gives the fabricator weeks to book instruments and build a test rig, and the owner's witnesses arrive having read it.

We recommend approving the FAT protocol in the same review as the drawings.

AeroSano hygienic air handling, built and FAT-witnessed to the approved specification

Related

More on this subject

10–15 Pa for FDA, 10 Pa for Annex 1: one cascade

FDA's 2004 aseptic guidance asks for at least 10–15 Pa between rooms of different classification; Annex 1 gives at least 10 Pa as guidance. Setting each cascade step at 15 Pa meets both. Holding it is harder: seals wear and filters load, so trend the differentials instead of waiting for alarms.

InsightRead