Why solvent vapour passes straight through a HEPA filter

  • Manufacturing & Distribution
  • 1 min read

The exhaust behind a solvent smell in the corridor runs through an H14 filter that passed its leak test last month.

The filter is doing what it is rated for: H14 under EN 1822 means at least 99.995% efficiency at the most penetrating particle size, a particle rating. A particle that touches a fibre stays on it, while a solvent molecule comes off again and travels on with the air.

Nor does the leak test help: it challenges the filter with an aerosol and looks for particles downstream, so vapour is not part of it. A second HEPA stage in series does nothing for the smell.

Vapours and gases need a different stage: adsorption on activated carbon or another medium chosen for the compound, or scrubbing for gases that dissolve or react. ISO 10121 is the test standard for gas-phase media and devices. Sizing starts from the compound, its concentration and the airflow, and in a humid climate from the moisture too, because water takes up capacity on carbon.

Where emission limits allow, the cheaper answer is often no treatment at all: exhaust the room once-through and discharge well away from any air intake.

Topics

Related

More on this subject

Why two teams give the same failure mode 40 and 160

A risk priority number is three judgements on ranked scales, multiplied, so two competent teams can score one failure mode 40 and 160. ICH Q9(R1) says subjectivity cannot be completely eliminated but may be controlled. In practice: define the scoring scales, record the assumptions behind each score and use relevant data where it exists.