Door swing and the pressure cascade

  • Manufacturing & Distribution
  • 1 min read

Several times a shift, the door between the room and its corridor drifts open by itself, a few millimetres.

Nothing is wrong with the latch. The room is 15 Pa above the corridor and the door opens outwards, towards the lower pressure. On a 0.9 m × 2.1 m leaf, 15 Pa is a steady push of about 28 N working to lift the door off its seal. Each time the closer loses, air escapes through the gap and the room pressure alarm chatters.

Turn the door round and the same 28 N holds it shut against the seal. Swing doors should normally open to the high-pressure side and be provided with self-closers: that sentence is in the WHO HVAC guideline for non-sterile products (TRS 1010, Annex 8).

Escape routes are the exception, and the guideline names them: exceptions to the swing direction should be justified and may include fire escapes or other health and safety measures, and in those cases the door closer mechanisms should be carefully controlled. In practice the closer is chosen for the pressure. The 28 N acts at mid-width, a moment of about 13 N·m at the hinges, and the closer has to hold more than that.

Most wrong swings begin on the architectural drawing, set by the furniture layout before the pressure cascade exists. Putting door swings and room pressures on one drawing makes the conflict visible.

How many doors on your cascade open towards the low side, and how many of those are escape doors?

Related

More on this subject

Energy measures that change validated cleanroom conditions go through Annex 15 change control. Classification alone can mean 10 sample locations for a 50 m² room, at rest and in operation, before recovery tests and a CCS update. Price that next to the kWh, or design reduced modes in and qualify them once.

InsightRead

Seven HVAC documents, indexed before the inspection

Cleanroom inspectors ask for the same HVAC evidence: qualification report, pressure trends and alarm log, HEPA leak tests, classification and recovery, smoke studies, as-builts and change controls. Index them per room, with document number, revision and location, so the back room answers in minutes.

InsightRead

Three APS runs across all shifts, and the HVAC has to hold still

Annex 1 initial validation of an aseptic process needs at least 3 consecutive successful simulations covering all working shifts, then periodic runs twice a year per process, line and shift. The cleanroom must hold its qualified state throughout. Agree an HVAC freeze date with QA, and list in advance which jobs are like-for-like and which need an impact assessment.

InsightRead