The panel passed its factory test. Then it was trucked to site, lifted by crane and cabled by a different crew.

None of that was in the FAT. Before the incomer is closed for the first time, five checks, each with a signature:

  1. Power off, doors open, look inside. Transit damage, swarf and cable offcuts are dealt with. Busbar joints and terminals are torqued to the maker's values and paint-marked.
  2. Insulation resistance is measured phase to phase and phase to earth, and the value is written down. IEC 60364-6 gives 500 V d.c. and at least 1 MΩ for circuits up to 500 V. Surge arresters, drives and electronic cards are disconnected or protected first, as their makers instruct.
  3. Every breaker and relay setting is compared with the protection coordination study. Settings left as delivered are the usual finding.
  4. Earth continuity is proved, and phase rotation is checked at the incomer before any motor is started.
  5. Tools are counted out, shrouds and covers are back on, and the labels and the single-line diagram match what was installed.

Write the insulation reading down as a number and not as a tick. A reading that passes today and has halved after a wet month in an unconditioned plant room is a warning.

The control panels and MCC/MDB we supply are built to IEC 61439, and every unit is FAT-tested and witnessed.

Talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)

Related

More on this subject

Five things a package needs before IQ

IQ should start from a verified installation. Before a turnover package moves from construction to qualification it needs a marked boundary, every IQ-blocking punch item closed, commissioning and balancing results, walked-down as-builts, calibration certificates and the equipment file. If one is missing, the package goes back.

InsightRead

GEP: what qualification can rely on, and what it repeats

Good engineering practice is the design review, installation checks and commissioning that sit under qualification. WHO's HVAC guideline defines it, and EU GMP Annex 15 (2015) allows data from outside the manufacturer's own programs if justified and controlled. Commissioning sheets made with calibrated instruments and signed by the person who measured can then be relied on.

InsightRead

Grade B at rest: state the equipment condition

Grade B at rest is held to 3,520 particles ≥0.5 µm and 29 ≥5 µm per m³. Annex 1 (2022) defines at rest for GMP grades as HVAC running, main equipment installed and standing by, and no personnel, reached after a clean-up period of under 20 minutes as guidance. The protocol should record that condition.

InsightRead