The panel passed its factory test. Then it was trucked to site, lifted by crane and cabled by a different crew.
None of that was in the FAT. Before the incomer is closed for the first time, five checks, each with a signature:
- Power off, doors open, look inside. Transit damage, swarf and cable offcuts are dealt with. Busbar joints and terminals are torqued to the maker's values and paint-marked.
- Insulation resistance is measured phase to phase and phase to earth, and the value is written down. IEC 60364-6 gives 500 V d.c. and at least 1 MΩ for circuits up to 500 V. Surge arresters, drives and electronic cards are disconnected or protected first, as their makers instruct.
- Every breaker and relay setting is compared with the protection coordination study. Settings left as delivered are the usual finding.
- Earth continuity is proved, and phase rotation is checked at the incomer before any motor is started.
- Tools are counted out, shrouds and covers are back on, and the labels and the single-line diagram match what was installed.
Write the insulation reading down as a number and not as a tick. A reading that passes today and has halved after a wet month in an unconditioned plant room is a warning.