The unit is on site, installed and powered. IQ is booked for Monday. The material certificates are still in someone's inbox at the factory.
That gap is common, and it is avoidable. IQ verifies that what was installed matches what was specified, and that the proof exists. If the documentation is being reconstructed after delivery, IQ waits for it, or worse, goes ahead on records assembled from memory.
We compile the equipment file during production, as each record is created:
- Material certificates, traced to the unit they belong to
- Weld and passivation records wherever stainless steel is involved
- The FAT report, with witnessed results and punch items closed
- The O&M manual and the recommended spares list
The practical effect is that IQ starts from a complete record rather than a request list. IQ cannot sign off a unit whose material certificate is missing.
If you buy hygienic AHUs, FFUs or pass boxes, ask the supplier before you order: is the equipment file built during production, or after delivery?