You have taken over a facility, or a design package someone else started.
The drawings look reasonable. Nobody can tell you whether it will pass qualification.
Before you change anything, get a written gap assessment. Not a site walk and an opinion: a document you can put in front of management now and in front of an inspector later.
What a useful one contains:
- The reference. Your URS, the target regulations (EU GMP, WHO GMP or US FDA cGMP) and the standards the design claims to meet. If there is no URS, writing one is the first finding.
- Evidence, not impressions. Document review against as-built conditions, plus spot measurements where they matter: room pressures, airflow, particle counts, AHU casing and filter condition.
- Findings graded by risk: critical, major, minor. A reversed pressure between grades does not sit in the same list as a missing label.
- For each finding, the fix, its cost range and its effect on schedule. That is what turns a report into a decision.
- What can stay. An assessment that only lists problems overstates the budget; it should also say which equipment and documents are usable as they are.
The assessment is usually one of the cheapest documents in the project, and it sets the budget for everything after it.