Taking over a facility: start with a written gap assessment

  • Engineering Solution & Consultancy
  • 1 min read

You have taken over a facility, or a design package someone else started.

The drawings look reasonable. Nobody can tell you whether it will pass qualification.

Before you change anything, get a written gap assessment. Not a site walk and an opinion: a document you can put in front of management now and in front of an inspector later.

What a useful one contains:

  1. The reference. Your URS, the target regulations (EU GMP, WHO GMP or US FDA cGMP) and the standards the design claims to meet. If there is no URS, writing one is the first finding.
  2. Evidence, not impressions. Document review against as-built conditions, plus spot measurements where they matter: room pressures, airflow, particle counts, AHU casing and filter condition.
  3. Findings graded by risk: critical, major, minor. A reversed pressure between grades does not sit in the same list as a missing label.
  4. For each finding, the fix, its cost range and its effect on schedule. That is what turns a report into a decision.
  5. What can stay. An assessment that only lists problems overstates the budget; it should also say which equipment and documents are usable as they are.

The assessment is usually one of the cheapest documents in the project, and it sets the budget for everything after it.

Talk to an engineer about yours: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)

Industries

Related

More on this subject

A process validated at the sending site was validated with that site's equipment, utilities and people. WHO's technology transfer guideline defines validation batches as those produced by the receiving unit, and EU GMP Annex 15 (2015) covers site transfers. The earlier validation supports the new protocol. With bracketing, the number of batches could be reduced; the content of the previous validation should be available.

InsightRead

The room data sheet changes jobs at qualification

A room data sheet begins as a design input that changes weekly and ends as the qualified record behind OQ, PQ and monitoring limits. Each role needs different revision control. Agree the freeze point before DQ, so design and QA are never editing different versions of the same room.

InsightRead