0.335: one constant from airflow to kilowatts

  • News
  • 1 min read

0.335 watts: what one m³/h of air carries for each kelvin of temperature difference.

Sensible heat in watts is 0.335 × airflow in m³/h × temperature difference in K. So 10,000 m³/h of supply air warmed by 10 K is carrying 33.5 kW. The sum fits on the back of a commissioning sheet and it settles arguments: whether a room's heat gain matches its airflow, whether a reheat coil is doing 5 kW or 50.

The constant is air density times specific heat, 1.2 kg/m³ × 1.006 kJ/kg·K, divided by the 3,600 seconds in an hour. US catalogues write the same relation as 1.08 × cfm × °F. It helps to know where it comes from, because the first of those inputs moves.

1.2 kg/m³ is air near 20 °C at sea level. At about 1,500 m the density is close to 1.0 kg/m³ and the constant falls to roughly 0.28, so the same fan volume carries about a sixth less heat. Warm air after a heating coil is lighter too.

It also counts sensible heat only. On a fresh air coil in a tropical wet season most of the load is latent, and 0.335 says nothing about that part.