FDA's 2004 aseptic processing guidance asks for at least 10–15 Pa between adjacent rooms of different classification, doors closed.
Annex 1 gives 10 Pa as a minimum guidance value. One design can meet both.
The two documents arrive at nearly the same number from different directions. The FDA guidance states it as 10–15 Pa, or 0.04–0.06 inches of water. EU GMP Annex 1 says adjacent rooms of different grades should have a differential of at least 10 Pa, as a guidance value, and expects the differentials to be monitored with alarms. For a plant that ships to both markets, setting each step of the cascade at 15 Pa sits inside both texts.
The harder part is holding it. A cascade balanced at 15 Pa at commissioning can read 8 Pa a year later if door seals wear, ceiling tiles are lifted and not resealed, or filters load and the supply fan runs out of margin. None of that shows on the day of the OQ.
So the design needs margin, and the monitoring needs to trend. A differential that slides over months is visible in the trend long before it trips an alarm, and that is when it is cheap to fix.
We fix the destination market in the design basis on day one, so the cascade is set for the evidence the plant will have to produce.