IEEE 519 is measured at the point of common coupling. In a fab fed at 22 kV, the process tools sit a long way downstream of it.
A plant can meet its IEEE 519-2022 TDD limit, set by the short-circuit ratio, at the 22 kV bus and still hand a tool a distorted voltage. The harmonic current is generated inside the fence: fan walls on the make-up and recirculation units, variable-speed pumps, chiller drives. A 6-pulse drive with a DC choke draws current at 35 to 42% THDi; without one, 65 to 75%. On a shared LV bus, that current through the transformer impedance becomes voltage distortion, and every load on the bus sees it.
Where the distortion ends up is fixed early, in the single-line diagram. Separate transformers for tool loads and mechanical loads keep fan and pump harmonics off the tool bus. DC chokes belong in the drive specification, since adding them after purchase means a variation and a site retrofit. Active harmonic filters are sized from a harmonic study of the actual drive list, to a design target of THDi ≤ 5% at the PCC.
The PCC figure does not cover a second check: voltage THD at each tool bus against the tool maker's facility requirement. Ask for that requirement with the tool hook-up data and measure it at commissioning, while there is still room in the switchroom for a filter.
We design LV and MV distribution up to 22 kV.
Industries