30%: the floor for a monthly generator test

  • Manufacturing & Distribution
  • 1 min read

Idling a standby diesel generator for half an hour every month slowly fouls its injectors.

The no-load run does show that the set starts. But a diesel running light never reaches working temperature. Fuel burns incompletely, and carbon and unburned fuel build up in the exhaust and on the injectors. Engine people call it wet stacking. The set that has started faithfully every month is then asked for full load on the day the grid fails.

NFPA 110, the US standard for emergency and standby power systems, sets the monthly exercise for diesel sets at a minimum of 30 minutes, in one of two ways: at a load that holds the exhaust gas temperature the manufacturer recommends, or at operating temperature and not less than 30% of the standby nameplate kW rating.

Thirty percent is a floor. On a pharmaceutical site the better test transfers the real load, AHUs, chillers, BMS and cold rooms, with the transfer switch doing its job.

Whatever the load, write it down: kW carried, minutes run, coolant and exhaust temperatures, oil pressure.

When did your generator last carry 30% for half an hour?

Related

More on this subject

A vendor IQ/OQ protocol and the URS lines it leaves out

A supplier's standard IQ/OQ protocol was written for the standard machine, before your URS existed. EU GMP Annex 15 (2015) says site personnel should confirm its suitability before approval, and that vendor protocols may be supplemented. Trace each URS line to a test, then write a short supplementary protocol for the lines left uncovered.

InsightRead

Batch records and the room data behind them

Under EU GMP Chapter 4, paragraph 4.11, a product with a 5-year shelf life keeps its batch documentation for at least 6 years. Environmental and BMS data that supported release is safest kept for the same period, so historian retention and storage belong in the URS for the BMS and EMS.

InsightRead

Set a device assembly room's class from the product's risk

ISO 13485 §6.4.2 asks for documented contamination control without naming a cleanroom class. Setting the class from sterilisation method, patient contact and bioburden sensitivity often lands device assembly at ISO 8, with ISO 7 only where needed, less air than Grade C, a smaller AHU and a reason an auditor can read.

InsightRead