Reading a thermography report for electrical panels

  • Manufacturing & Distribution
  • 1 min read

A loose lug at half load shows about a quarter of the temperature rise it would show at full load.

Heat at a bad joint rises roughly with the square of the current, so a thermal scan of lightly loaded panels finds little, and the report then says the panels are fine. On the survey report, look for these entries:

  1. Load at the time of the scan, per circuit. NFPA 70B (2023 edition, since replaced by the 2026 edition) says the inspection shall be performed at normal circuit loading; where that is not feasible it permits not less than 40 percent of nominal circuit loading, and the loading shall be documented.
  2. Line of sight. Covers were opened under the site's electrical safety procedure, or the panel has infrared windows. A camera cannot see through a steel door or a clear plastic shroud.
  3. Emissivity. Bare copper and aluminium reflect, and a shiny busbar can read cold while it is hot. The reading should come from a painted, taped or oxidised surface.
  4. A reference. Each phase is compared with the other two and with similar circuits at similar load. One absolute temperature means little.
  5. A record that leads somewhere: thermal and visible image, temperature difference, severity, action. Then a second scan after the repair.

Book the survey for a production day in the hot season, when chillers and AHUs draw their real current.

How loaded were your panels the last time they were scanned?

Related

More on this subject

Ring main units for a 22 kV plant supply

With a ring main unit, a faulted section of a 22 kV loop is isolated by switching instead of waiting for the repair. Inside: ring load-break switches, a transformer feeder and interlocked earthing switches, with a sealed utility metering cubicle alongside. The plant stays dark until the switching is done, so plan the cleanroom restart.

InsightRead

A night-time 40% THDi reading on a lightly loaded EC fan wall can be 4% TDD at the point of common coupling. IEEE 519-2022 limits TDD, relative to maximum demand current, and the limit steps with ISC/IL at the PCC. Decide on active filtering from a study, not one feeder reading.

InsightRead