A change-order log an owner can run

  • Project Management Consultancy
  • 1 min read

40 change orders at 0.5% of the contract each add up to 20%, and nobody ever approved a 20% overrun.

That is a common way for a GMP project budget to drift. No single change is big enough for a board decision, and the cumulative total never appears on one page until the final account.

A log the owner can run needs only a few columns and three rules behind them.

  1. Every instruction gets a number, the date it was raised and a date by which the contractor must price it, with the number of days written into the contract. Unpriced changes are where the arguments at final account come from.
  2. The owner signs the priced change, cost and time, before anyone on site acts on it. A genuine emergency is the exception, and then the instruction carries a not-to-exceed figure and is priced afterwards on the same log.
  3. Each row adds its cost to the budget and its days to the completion date, including changes priced but not yet approved. The owner reads the running total every week, rather than the individual rows.

Our EPCM monthly reports carry schedule, cost, earned value and risk. Approved and pending changes belong inside those cost and schedule figures, not in an appendix nobody opens.

How our project management consultancy works

Related

More on this subject

A month-end note from Tony Nguyen, CEO

After more than twenty years with automation vendors and running an EU-GMP EPC contractor, Tony Nguyen saw problems start at the handovers between companies rather than inside any one scope. This note explains why Humiley is organized as one accountable team across design, project management, equipment and maintenance.

InsightRead

Calibration dates and the commissioning program

A calibration certificate that expires partway through air balancing leaves the later readings without a traceable instrument at OQ review. Before commissioning, list every instrument that will produce a qualification reading, check each due date against the whole test window plus slippage, and record the serial on every test sheet.

InsightRead