Calibration dates and the commissioning program

  • Engineering Solution & Consultancy
  • 1 min read

A calibration certificate that expires halfway through air balancing can put every reading taken after that date in question.

The way it happens is ordinary. Balancing runs over three weeks, the anemometer was calibrated eleven months before it started, and nobody set the due date against the test program. At OQ review someone lines up the test dates with the certificate. Readings after expiry have no traceable instrument behind them, and the options are an as-found check with an impact assessment, or repeating the tests.

The fix is dull and cheap. Before commissioning starts, list every instrument that will produce a qualification reading, with serial number and calibration due date. Check each due date against the end of the planned test window, plus a margin for the slippage every program has. Then write the instrument serial on every test sheet, so the link is on paper when an auditor asks.

It is one control of an ISO 9001-aligned QMS, and like the others it only counts if someone checks it on site: current drawing revisions at the gate, material certificates checked before installation, deviations logged at the FAT bench when they are found.

Humiley's EPCM work runs an ISO 9001-aligned QMS on the project itself, with FAT, SAT, commissioning and qualification records in one chain.

When did someone last compare instrument due dates with your commissioning program?

Related

More on this subject

Grade B at rest: state the equipment condition

Grade B at rest is held to 3,520 particles ≥0.5 µm and 29 ≥5 µm per m³. Annex 1 (2022) defines at rest for GMP grades as HVAC running, main equipment installed and standing by, and no personnel, reached after a clean-up period of under 20 minutes as guidance. The protocol should record that condition.

InsightRead

How to correct a GMP record

EU GMP Chapter 4 asks that any alteration is signed and dated, leaves the original readable and records a reason where appropriate. Correction fluid, overwritten digits and blacked-out entries all break that rule and ALCOA+. Engineering and site teams need it in their induction as much as QA.

InsightRead