Cleanroom setback: timer or particle counts

  • News
  • 1 min read

Cleanroom airflow set back at night on a timer is easy to validate. It also has no idea whether anyone walked in at 2 a.m.

ISO 14644-16 covers reducing cleanroom airflow when a room does not need full flow, whether the reduction follows a time schedule or the particle counts in the room.

A schedule drops airflow in fixed periods and restores it before production. Validation needs a setpoint per period, a proven recovery time and a trend of the switch. What it misses is off-schedule work, such as a night maintenance job or a weekend cleaning crew working under reduced flow.

With particle-driven control the counters set the flow, so airflow follows what is happening and saves more on quiet nights. The counters, their alarm logic and their failure modes then become part of the validated system. A counter that fails or reads zero has to send the system to full airflow, and that default needs its own test at OQ.

The recovery test applies to both. Before operations restart, show that the room comes back from the setback state to its at-rest limits, with pressure differentials stable, within the time the procedure allows. When the setback settings change, prove the recovery again.

Our opinion: plants with disciplined change control and a well-maintained monitoring system get more out of particle-driven control. Elsewhere, start with a schedule and prove it.

What does your setback do when a counter goes offline?

Related

More on this subject

Periodic requalification: what is retested and how often

EU GMP Annex 1 (2022) sets maximum requalification intervals: 6 months for Grade A and B cleanrooms and 12 months for Grade C and D. Classification, HEPA leak tests, airflow volume, pressure differentials and air velocity, or recovery where airflow is not unidirectional, are retested. A risk assessment can shorten these intervals, never extend them.

InsightRead

Three APS runs across all shifts, and the HVAC has to hold still

Annex 1 initial validation of an aseptic process needs at least 3 consecutive successful simulations covering all working shifts, then periodic runs twice a year per process, line and shift. The cleanroom must hold its qualified state throughout. Agree an HVAC freeze date with QA, and list in advance which jobs are like-for-like and which need an impact assessment.

InsightRead