An OQ report can hold a certificate for every test instrument and none for the room pressure transmitters it reads.
Those transmitters are often calibrated at the vendor's factory before shipping. By OQ that can be months earlier, with a wet season and a site installation in between. If one has drifted, the pressure cascade in the report is a figure nobody can defend.
EU GMP Annex 15 includes calibration of instrumentation in the IQ checks. 21 CFR 211.68(a) wants automatic and electronic equipment routinely calibrated or checked, and 211.160(b)(4) bars instruments that fail their calibration specifications.
The test kit has a trap of its own. A particle counter calibrated last year can fall due halfway through the OQ window, and every count taken after the due date becomes a deviation.
Before the first test, one sheet can cover both groups:
- Test instruments brought in: particle counter, anemometer or capture hood, micromanometer, data loggers.
- Installed sensors the protocol reads: room differential pressure, temperature and RH transmitters, filter gauges.
For each item, record the certificate number, the due date checked against the last day of the test window, and the calibrated range checked against the value to be tested. Put that sheet at the front of the OQ.