Lactose, starch and microcrystalline cellulose all burn as dust clouds, and all three end up in the granulation dust collector.
The collector is one of the places in an OSD plant where fine combustible dust is concentrated in a closed box on purpose, along with fluid-bed dryer filters and mill collectors.
Send a sample of the actual blend for explosibility testing before the collector is specified. If it is combustible, the protection options are venting (a panel that bursts and releases the explosion to a safe place), flameless venting where the unit has to sit indoors, or chemical suppression. Each needs isolation on the inlet duct, so a deflagration cannot run back into the granulation room.
That result also fixes where the collector goes. Venting to a safe area puts it outside or on an external wall. The duct from the room then gets longer, and needs enough velocity to keep powder moving, with cleaning points where it can still settle.
The filter media is the easier call. Pleated cartridges pack a lot of filter area into a small housing and suit fine, dry pharmaceutical dust; bags cope better with heavy, sticky or fibrous loading and higher temperatures, and need more height. For potent products, how the filters come out weighs more than either: a safe-change or bag-in/bag-out housing and a sealed discharge for the collected dust.