Emergency repairs: fix first, then the change record

  • Life Sciences
  • 1 min read

A supply fan motor on a Grade C AHU has failed with product in the room, and the cascade has gone with it.

Nobody is going to wait for Thursday's change control board.

Nor should they. The GMP question is what the record shows in the morning. A sequence that holds up:

  1. Contain. Protect or stop the product in the affected rooms, note when the alarm came in, and tell QA before anyone opens the unit.
  2. Repair like-for-like where you can: same rating, same frame, same speed. A like-for-like replacement is usually a maintenance record. A different motor, a new drive or changed parameters is a change.
  3. If it is a change, raise it retrospectively the same day, with the reason it could not wait.
  4. Assess the impact. Did pressures reverse? How long was the room out of grade? Which batches were inside? Does the CCS need a look?
  5. Decide on requalification and record the decision either way. After a like-for-like swap, checking airflow and pressure differentials may be enough. After a different fan, more is.

EU GMP Annex 15 section 11 still applies; the emergency route only changes the order of the steps. Write that route into the change control procedure before the night you need it.

Our maintenance service includes 24/7 corrective and emergency response across Southeast Asia under a maintenance agreement.

Does your procedure have an emergency route, or does it rely on whoever is on call?

Industries

Related

More on this subject

Four maintenance KPIs for a GMP plant

A single PM compliance percentage hides the overdue task QA cares about. Track PM compliance by criticality, overdue critical tasks listed by name, repeat failures on the same asset, and mean time to restore the pressure cascade from the BMS trend. All four need a CMMS asset register with criticality assessed.