A layout revision after award adds forty square metres of cleanroom wall panel. Who pays was settled when the contract form was chosen.
On a lump sum the contractor priced the tender drawings, so the extra panel becomes a variation, quoted while the contractor is mobilised and the owner has little room to negotiate. Had the same forty square metres simply been missed in the contractor's take-off from unchanged drawings, it would have been the contractor's loss.
Put that revision on a remeasurable contract, with fixed rates against a bill of quantities, and it is measured and paid at the bill rate for panel. The owner now carries the quantity risk, and the price stays an estimate until the final account. Somebody on the owner's side also has to measure, to rules agreed at tender, including whether panels count gross or net of doors.
Many cleanroom packages are split. AHUs, FFUs and pass boxes are defined items that price well as a lump sum. Ductwork, pipework, cable and panel area move with every layout revision and suit measurement.
In stage-gate delivery this call belongs at the gate where the layout is frozen enough to price.