OQ airflow: check every terminal, not only the room total

  • Life Sciences
  • 1 min read

Four HEPA terminals can add up to the right room airflow while one of them delivers 60% of its design flow.

Take a 6 × 4 × 3 m Grade C room: 72 m³, designed for 25 air changes, so 1,800 m³/h from four terminals at 450 m³/h each. The flow hood readings come back 520, 510, 500 and 270. The total is 1,800 m³/h, exactly 25 ACH, and a room-total criterion passes.

The fourth terminal sits at 60% of design while the other three run 11 to 16% high to make up for it. Usual causes: a damper left nearly shut during balancing, a flexible duct crushed above the ceiling, a filter loading on one side. The corner under that terminal gets less dilution, and it is where a recovery test or an in-operation count goes wrong later, long after the airflow test was signed.

So the OQ protocol needs two acceptance criteria. One for the room total against design, and one for each terminal against its own design flow, with the tolerance written down. Record the instrument and any correction factor used for the terminal face beside each reading.

A terminal that far below design gets rebalanced and measured again before the recovery test starts.

More on our news page

Industries

Related

More on this subject

What ends the life of a HEPA filter

EU GMP Annex 1 (2022) asks for an integrity test of final filters at requalification and puts no age on the filter. A terminal HEPA is replaced when a leak cannot be repaired within site limits, when pressure drop reaches the manufacturer's final value, or after damage or wetting. On glass-fibre media, dust loading alone does not lower efficiency.

InsightRead

AHU casing deflection: D1 or D2

EN 1886 classes AHU casing strength by deflection at test pressure: D1 up to 4 mm/m, D2 up to 10 mm/m. On a high-static GMP supply unit, a flexing panel works its gaskets loose and leakage rises. Ask which class was tested, on what model box, and whether your design pressure fits.

InsightRead

Bag-in/bag-out: a contained filter change

In a potent-compound suite the exhaust HEPA collects the compound for its whole life. A bag-in/bag-out housing needs gas-tight isolation dampers, a bag change in which the ring never opens to the room, ports for in-place leak testing and space to work the bag, plus a written procedure and trained technicians.

InsightRead