An EU GMP certificate for a plant outside Europe comes after an inspection by an EEA authority, and the result is public.
The certificate, or a statement of non-compliance if the inspection goes badly, is entered in EudraGMDP, the EU database anyone can search. Sites in countries covered by an EU mutual recognition agreement follow a different route; for a plant in Viet Nam, plan on an inspection.
The usual route, in outline:
- An EU partner starts it. Normally the importer or the marketing authorisation holder names the site, and the request goes to the competent authority that supervises that importer.
- The site sends its Site Master File.
- The authority schedules the inspection, which covers the quality system as well as the premises, the HVAC and the utilities.
- The report grades deficiencies as critical, major or other. The site replies with a CAPA plan and evidence, within the time the authority sets.
- When the replies are accepted, the certificate is issued and entered in EudraGMDP.
Two things usually set the pace. The dossier and the importer relationship have to exist before anyone books an inspector. And the plant's evidence is far easier to show when it was produced during the project rather than assembled afterwards.