GMP sets no 12-month calibration interval

  • Life Sciences
  • 1 min read

Nearly every instrument list carries a 12-month calibration interval, and few sites can say where the figure came from.

The 2015 text of EU GMP Chapter 3 says measuring, weighing, recording and control equipment should be calibrated and checked "at defined intervals by appropriate methods". 21 CFR 211.68 says equipment shall be routinely calibrated, inspected or checked according to a written program. Neither names a period.

The nearest thing to a figure is WHO's storage and transport guidance: monitoring devices in a store calibrated at least once a year, unless otherwise justified. A storage default, with its exception written in.

The calibration laboratory cannot settle it either. Under ISO/IEC 17025 a certificate shall not carry a recommendation on the calibration interval unless that was agreed with the customer.

That leaves the interval with the site, and it needs a basis. Two inputs do most of the work: what a wrong reading from this instrument would let through, and the as-found results of past calibrations. An instrument found well inside tolerance several times running can go longer; one found near the limit twice should come in sooner.

Legal metrology is a separate obligation: national rules may fix a verification cycle for some instrument types.

Most of the list will stay at 12 months. What changes is one line of rationale per instrument class in the calibration procedure, and the few instruments that move.

Topics

Industries

Related

More on this subject

Grade B change rooms: one room or two

EU GMP Annex 1 calls separate entry and exit change rooms for Grade B desirable. One room saves area but relies on procedure at the busiest shift change; two rooms give one-way flow at the cost of doors, air and qualification. On a new build, start from two.

InsightRead

Grade C through a fab engineer's eyes

To a semiconductor engineer, Grade C at ISO 8 in operation looks loose. EU GMP Annex 1 adds microbial limits: 100 CFU/m³ in air, 50 per settle plate over 4 hours, 25 per contact plate. Rooms wiped with sporicide need floors and joints a fab never had to clean, and a CCS that ties the choices together.

InsightRead

Handling a deviation: secure the evidence in the first hour

An hour after a deviation is found, the room may be cleaned and the controller's trend close to being overwritten. Record it as found, contain it and export the data first. Then classify by risk, investigate the root cause with evidence, set corrective and preventive actions with owners, and have QA close and trend it.

InsightRead