Classifying a Grade A zone at 0.5 µm takes about 6 litres of air per location, not a cubic metre.
The 1 m³ figure many protocols still carry came from the 2008 Annex 1. The 2022 text sends you to ISO 14644-1 for sampling locations (4.28) and sets no sample volume of its own.
ISO 14644-1:2015 sizes the sample from the class limit at the largest particle size counted: enough air to expect 20 particles at that limit, and never less than 2 litres or 1 minute. Grade A at 0.5 µm is 3,520/m³, so 20 / 3,520 × 1,000 ≈ 6 litres. On a 28.3 L/min counter the 1-minute floor governs.
So the sample is not what fills the day. Three other things are.
Locations. ISO 14644-1 sets the minimum from the area, and Annex 1 adds critical points such as the point of fill and the stopper bowl, chosen by documented risk assessment.
States. Classification runs at rest and in operation (4.27, 4.29), and the in-operation run needs the line working or simulated with the full crew.
5 µm. Annex 1 leaves it unspecified for Grade A classification unless the CCS or trends call for it. The volume follows the limit at the largest size counted, so with a limit in the tens per m³ each location needs hundreds of litres.
The OQ plan should list locations, states and sizes, with time per location worked out from counter flow and sample volume. Agree counter calibration, flow and tube length before the protocol is approved.
Which particle sizes does your Grade A protocol count?