Replacing one AHU while the rooms next door hold grade

  • Manufacturing & Distribution
  • 1 min read

Within minutes of one AHU being switched off in a running GMP plant, the room across the wall feels it.

A room holds its differential because supply, return and leakage are in balance, and some of that leakage runs through doors into rooms served by another unit. Once those rooms become a work zone held negative, more air leaks out through the shared door and the differential falls. A 10 Pa step between grades can disappear without anyone touching the running system.

Most of the planning therefore goes into the neighbours. A common exhaust fan, a shared return plenum, a transfer grille or a pass box in the boundary wall will carry air between the live side and the work zone, so each is sealed before the unit stops.

The running system then usually needs a temporary trim on the return or exhaust dampers of the boundary rooms until their differentials are back on target. Write down every original damper position before anyone moves it; the same positions are needed when the new unit is balanced.

Alarm limits are where a team is tempted to cut a corner, because widening them stops nuisance alarms during the works. We would keep EMS limits at their validated values, route the alarms to someone on the job, and put any temporary change to a setpoint or limit through change control.

We take work from a single AHU replacement in a running facility up to a full greenfield plant.

How we work, from one AHU to a greenfield plant

Industries

Related

More on this subject

Calendar PM vs criticality-based PM

Calendar maintenance gives every asset the same interval, so when hours run short the critical ones suffer with the rest. Scoring assets by the consequence of failure moves effort toward what holds a grade or a pressure cascade, and is best done once from the project's asset register.

InsightRead

Four checks at the basic-design gate

Before detail design opens, a GMP project should have frozen room data sheets and pressure cascade, loads that match the equipment list, a URS for each critical system and owned open items. A cascade change after the ducts are drawn reaches the duct sizes, terminal filters, AHU selection and every neighbouring pressure step.

InsightRead

Four maintenance KPIs for a GMP plant

A single PM compliance percentage hides the overdue task QA cares about. Track PM compliance by criticality, overdue critical tasks listed by name, repeat failures on the same asset, and mean time to restore the pressure cascade from the BMS trend. All four need a CMMS asset register with criticality assessed.

InsightRead