A material airlock at 20 air changes an hour needs about 14 minutes to bring particle levels down 100:1 after the outer door closes.
That comes from a dilution sum. With well-mixed air, the time is ln(100) ÷ 20 hours, and doubling the air change rate halves the wait. It is the number the transfer SOP should carry, and one reason the material airlock should not be drawn as a copy of the gowning room next door.
The personnel airlock is laid out around the gowning order: how many people change at shift start, the step-over bench, the mirror, where clean garments are kept. People pass through quickly, and the interlock only has to stop both doors opening at once.
Goods are slower and bigger. The largest trolley or pallet sets the floor area, plus space to wipe around it. A door stays open while the load crosses, so the interlock needs a hold-open timer with an alarm when the limit is passed, and the hold-time countdown should start only once the outer door has closed. A small display showing the time left stops operators guessing.
Annex 1 asks for separate personnel and material airlocks where practicable. A small plant that shares one room has to put the separation into a procedure that still works at shift change.
We lay out both airlocks from the people and material flow diagrams, then size the purge from the air change rate.