Six months after start-up, drums are going into Grade C through the personnel airlock, because no other door they fit was drawn.
That is a layout-stage mistake. A pass box went on the drawing where the drum flow was never checked, and nobody asked how often the route would be used either.
Size is the first check. A pass box takes one small load at a time behind interlocked doors, so both never open together. Anything on wheels, a cart, a drum or a pallet of components, needs a material airlock, and an airlock is a room with floor area, its own supply and exhaust, a wipe-down and disinfection step and a cleaning schedule.
Frequency is the second. Twenty transfers an hour through a box built for five turns into a queue, and a queue at an interlocked door ends with someone propping it open.
Pressure comes last. A dynamic pass box with its own HEPA-filtered airflow purges the chamber between transfers. An airlock has to hold its place in the room cascade, typically 10 to 15 Pa between adjacent grades, and whether it is built as a cascade, bubble or sink depends on whether the product, the room or both must be protected.
Each transfer route belongs in the contamination control strategy, with the item, the cleaning step and the airflow described for that route.
Pass boxes are part of Humiley's cleanroom equipment range.
What is the largest item your team moves into Grade C?