When terminal HEPAs reach their final pressure drop in months instead of years, look at what was in the ducts before the first fan start.
Whatever sits in a supply duct downstream of the air handler's last filter has one way out: through the terminal HEPA. On a construction site that means cement and gypsum dust, grinding swarf and insulation fibre.
The dust gets in through ordinary site routine: duct sections arrive uncapped and are stacked on the slab while other trades cut and chase around them, and during installation the open ends face the room overnight.
To keep it out, order the ductwork cleaned at the factory with every end capped, and store it off the floor. Re-cap every open end at the end of each shift; a supervisor's walk before leaving is what makes that happen. Look inside each section and wipe it before it is connected, and record it on the installation check sheet. Fit the terminal HEPAs last, after a blow-down with temporary media at the terminals.
A blow-down takes the loose dust and leaves what has stuck to the forming oil on new galvanised sheet.
ISO 14644-4:2022 calls for a clean build protocol in its construction clause. Which duct rules go into it is the project's decision, and they belong in the ductwork specification before the order is placed.
Who walks the open duct ends on your site at the end of the shift?