0.30 m/s in one corner, 0.45 m/s across the FFU array: the average passes, and that corner may sit over open product.
For Grade A unidirectional airflow, Annex 1 (2022) gives 0.36–0.54 m/s at the working position as a guidance value, with any other value to be justified. A mean inside that band tells you nothing about the spread.
Uniformity gets checked twice.
At FAT, each unit is measured on a grid of points across its filter face, and the fan speed setting is recorded. That record matters later, because an EC fan speed changed on site is otherwise invisible. The report should list every reading, the mean and each point's deviation from it, against the criterion written in the URS. Filter-face readings show uniformity; the Annex 1 band itself is checked at the working position.
At OQ the grid is repeated in place across the whole array, with the ceiling, lights and return paths as built. Now the result is a map. A healthy one looks flat. A low edge or corner usually points at something specific: a speed setting, plenum pressure falling away at the far end, a blanked panel, a light fitting disturbing the flow.
Ask for the full grid in both reports. It takes one page and it is the page you will want during an investigation.
Every FFU we supply is FAT-tested and witnessed, and the FAT report goes into the equipment file so OQ starts from a known baseline.