A plant room drawing shows where the AHU ends up. It says nothing about the goods lift the unit has to ride in first.
Section split and section weight are set by the tightest point on the delivery route, and that point is rarely in the plant room. Five checks, done before the general arrangement is frozen:
- Every door on the route, measured as clear opening after the frame and any threshold. The nominal door size on the architect's schedule is larger than the hole you get.
- The lift: internal car size, door opening and rated load, against the heaviest section plus its skates.
- Corridor turns. A long section needs the diagonal of the corner, not the corridor width.
- Crane lifts through a roof or wall opening: reach, capacity at that radius, and lifting lugs on each section.
- Floor loading along the whole route, including slabs over voids and any raised floor.
The trade-off is joints. Every extra split is another casing joint to seal on site, another gasket, another place for the leakage class the unit was built to (EN 1886 L1 or L2) to slip. If the route forces a unit into more sections, plan a casing leakage check after site reassembly, not only at FAT.