The fan passed its factory test and delivers short on site, because the elbow bolted to its outlet was calculated as an ordinary elbow.
The name for the missing pressure is system effect. Fan curves are measured to AMCA 210 or ISO 5801 with a uniform inlet and a straight duct on the outlet, long enough for the airflow to develop fully.
Put an elbow straight on the outlet, or a plenum wall close to the inlet, and the fan no longer works on its catalogue curve. It makes less pressure at the same speed. The ordinary elbow coefficient does not cover that loss, because it belongs to the fan and the fitting together.
AMCA Publication 201 handles it with system effect factors, read from charts for the geometry and added to the system pressure when the fan is selected. Its yardstick on the outlet side is the effective duct length: 2.5 duct diameters for outlet velocities up to 2,500 fpm (about 12.7 m/s), plus one diameter for each further 1,000 fpm.
At design, either give the fan its straight lengths, or add the factor and pay for it in fan power for as long as the plant runs. Found at commissioning, it usually ends in a larger motor.