A sag to 50% voltage for 200 ms is short enough that nobody on the floor notices it.
SEMI F47 expects a semiconductor tool to ride through it. It says nothing about the fan wall above the tool.
SEMI F47-0706 sets a ride-through curve for process equipment: sags to 50% of nominal voltage for 200 ms, to 70% for 0.5 s and to 80% for 1 s, without the tool stopping. Tool makers design to it because fabs buy to it.
The support systems are often bought to a different standard, or to none. EC fan drives trip on undervoltage. Contactors drop out when their coil voltage sags. A chiller controller resets. So after the sag the tool is still running, while the minienvironment or cleanroom around it has lost airflow, pressure and temperature control. The wafer was protected by the tool's design. The air around it was not.
The fix is to specify the support systems to the same curve. Put the F47 ride-through requirement into the specifications for fan drives, controls and contactors. Ask vendors for test evidence. Put the controls on UPS where ride-through cannot be designed in.
Our power design work covers LV to MV distribution up to 22 kV, and a sag study at design stage shows how often a site's supply will actually test that curve.
Does your fan-wall specification mention voltage sags at all?