Nightly backup of an EMS means up to 24 hours of room data can be lost. On most sites that figure came with the backup schedule.

It has a name. The recovery point objective, RPO, is the maximum age of data you accept losing. A backup at midnight is an RPO of 24 hours, written down or not.

Its partner is the recovery time objective, RTO: the longest the system may stay down before the process it supports is in trouble.

Backup frequency follows from the RPO. The RTO decides what stands ready when the server dies: a spare machine, a configuration image, a restore procedure and a person who has run it.

The 2011 text of EU GMP Annex 11 uses neither term. Clause 7.2 of the 2011 text says regular back-ups of all relevant data should be done, and the ability to restore the data should be checked during validation and monitored periodically. Clause 16 of the 2011 text says the time required to bring alternative arrangements into use should be based on risk. RPO and RTO turn "regular" and "based on risk" into numbers. IT can propose them. QA should sign them, because QA knows which batch decisions rest on the data.

Both are proven by a restore test. Time one, from bare server to trends on screen.

Industries

Related

More on this subject

Annex 11 supplier assessment belongs in the validation plan

EU GMP Annex 11 clause 3.2 makes supplier competence and reliability part of computerized system validation, with the need for an audit set by risk. For SCADA, BMS and EMS, supplier records can reduce the testing the user repeats; the URS, risk assessment and configuration tests such as alarm limits and user roles stay with the user.

InsightRead

EU GMP Annex 11 clause 7.2 asks for regular backups whose restore is checked during validation and periodically. Clause 17 asks that archived data stays accessible, readable and intact, with retrieval re-tested after system changes. A green nightly backup does not prove that old trend data opens after an upgrade.

InsightRead

GMP on the electrical side

Where a SCADA, BMS or EMS records GMP-relevant data, access control, clock synchronization, alarm records and audit trails are decided by the electrical and automation engineers. Many sites keep those parameters on a separate validated EMS. Humiley's cross-functional training covers GMP, validation and project management.

InsightRead