Why qualified rooms stay constant volume

  • Life Sciences
  • 1 min read

A classified room is qualified at the airflow it had during OQ, and VAV turns that airflow into a moving target.

The air change rate, the recovery time and the pressure step to each neighbour were all measured at one set of supply and extract flows. Change the flows and each of those results becomes a prediction.

So qualified rooms usually run at constant volume, meaning each room's supply and extract flows are held at their set values. The fan still varies. As filters load it has to speed up to hold the same flow, so a GMP supply AHU tends to have a variable-speed fan controlled on duct pressure or measured flow, and each room a constant-volume terminal that holds its set flow whatever the duct does.

With VAV, supply follows the cooling load. On a cool morning one room's supply falls, and its extract has to follow with the same offset or the pressure step changes size or even direction. The air change rate drops below the one the recovery test proved.

VAV still earns its place in offices, corridors outside the GMP zone, technical areas and unclassified stores, and on lab fume-hood exhaust where the supply is made to track it.

A reduced-flow setback for nights is qualified as a condition of its own, with its own pressures and recovery time: two set flows, each one proved.

Our cleanroom HVAC work covers pressure cascades for Grade A to D rooms.

Industries

Related

More on this subject

Zoning and Pressure Cascade

In pharmaceutical facility design, if the HVAC system is the "lungs," then the Zoning and Pressure Cascade strategy is the "immune system." It creates invisible but effective barriers that prevent microbial ingress and strictly control…

InsightRead

Value engineering after tender: savings that return at OQ

After an over-budget cleanroom HVAC tender, three savings recur: an EN 1886 L2 casing instead of L1, fewer room pressure transmitters, and deleted door drop-seals. Each can reappear as an OQ failure in airflow, alarm testing or pressure differentials, so check every line against its URS requirement and test before accepting it.

InsightRead

Four checks at the basic-design gate

Before detail design opens, a GMP project should have frozen room data sheets and pressure cascade, loads that match the equipment list, a URS for each critical system and owned open items. A cascade change after the ducts are drawn reaches the duct sizes, terminal filters, AHU selection and every neighbouring pressure step.

InsightRead