A pressure cascade that holds all day can reverse for a few seconds every time the AHU starts.

Room pressure is a mass balance: supply in, extract and leakage out. At steady state the controls hold the offsets. During a start or a stop there is no steady state, and whichever fan moves first decides which way the air goes through the door gaps.

For a positive suite, start supply before extract and stop extract before supply. The rooms go briefly more positive, never negative. A containment suite for high-potency product works the other way: extract first on start, supply first on stop, so the suite stays a sink throughout.

Writing that in the functional specification is the easy part. What we check before OQ:

  1. The order is interlocked, not just scheduled. On a containment suite, supply cannot run unless extract is proven running.
  2. A single fan trip has a defined response: the other fan follows, or ramps down on a set curve.
  3. Recovery after a power cut restarts in the same order, including when the generator picks up loads in stages.
  4. The OQ test uses a real power cut and a forced fan trip, with room differentials logged fast enough to see the transient, not just the start button and a steady reading.

Humiley designs the control sequences with the pressure cascade, so the same design basis covers the transient and the steady state.

Related

More on this subject

Value engineering after tender: savings that return at OQ

After an over-budget cleanroom HVAC tender, three savings recur: an EN 1886 L2 casing instead of L1, fewer room pressure transmitters, and deleted door drop-seals. Each can reappear as an OQ failure in airflow, alarm testing or pressure differentials, so check every line against its URS requirement and test before accepting it.