The load calculation inputs that are usually guessed

  • News
  • 1 min read

Most cleanroom load calculations are only as good as four or five inputs that were guessed on day one.

The software is rarely the weak point. The inputs we see guessed most:

  1. Equipment heat from the nameplate. A nameplate gives maximum electrical input, not the heat released into the room. Ask the vendor for heat-release data, split into room and exhaust.
  2. Lighting power density taken from a comfort-building table, long after the real lighting design exists.
  3. People at an office activity level. Gowned operators working a line release more heat than people at desks, and the count should come from the shift plan.
  4. Process heat from hot loops, autoclaves, washers and sterilisers. The process description says which run hot and for how long.
  5. Fan heat and duct gains. At 1,500 Pa total pressure and an overall efficiency near 60%, a fan with its motor in the airstream adds about 2 K to the supply air. Ducts through a hot ceiling void pick up more.

Every wrong input ends one of two ways. An oversized coil runs at part load and holds humidity poorly. An undersized one cannot hold the room on the first hot, wet afternoon. The heat balance and RTS methods in the ASHRAE Fundamentals handbook are fine; they need real numbers.

We build load calculations from the process description and vendor data, and select the AHU from that calculation.

Related

More on this subject

Set a device assembly room's class from the product's risk

ISO 13485 §6.4.2 asks for documented contamination control without naming a cleanroom class. Setting the class from sterilisation method, patient contact and bioburden sensitivity often lands device assembly at ISO 8, with ISO 7 only where needed, less air than Grade C, a smaller AHU and a reason an auditor can read.

InsightRead

The trace matrix gap only a backward read finds

A recovery test with a 20-minute limit, traced to a 15-minute URS requirement, passes and leaves the requirement unproven. Reading a trace matrix from each test back to its requirement finds these weak links and orphan tests. Pick three signed results at random and trace them back.

InsightRead