Every pipe, cable and sensor that passes through a cleanroom panel leaves a hole someone has to seal, clean and prove.
Most rooms are built with the penetrations drawn. Then late services arrive: a new sensor, an extra drain, a cable run that was forgotten. They go through wherever there is space, often in the ceiling void. The room holds its 10–15 Pa on paper and loses it through a gap nobody recorded.
What we ask for on every panel penetration:
- A sleeve fixed to the panel. A pipe pushed through a cut in the insulated core gives the sealant nothing to grip, and the core stays open to the room.
- Sealant on both faces, compatible with the site's disinfectants, finished with a flush cover plate on the clean side so there is no ledge to wipe around.
- One service per sleeve where possible. A bundle of cables through one hole cannot be sealed between the cables; use a cable transit or gland plate.
- A penetration schedule: location, service, the two rooms it connects, sleeve and seal type, checked at walkdown before the pressure test.
The schedule is the part that gets skipped, and it is the one an investigator asks for when a room fails its pressure differential at OQ.