Specify vision panels flush on both faces

  • Manufacturing & Distribution
  • 1 min read

A vision panel whose frame stands proud of the cleanroom wall is a shelf, and every shelf in a cleanroom collects particles.

It is an easy detail to miss at design review. The panel schedule says "vision panel, double glazed" and the elevation shows a rectangle. What arrives on site depends on the supplier, and a standard window frame fixed into a wall panel leaves a horizontal top edge on one or both faces. Cleaners wipe around it, and sooner or later it shows up in the surface monitoring results.

Specify it flush on both faces. A sealed double-glazed unit set into the panel so the glass sits level with the panel skin on the clean side, and on the other side as well where both rooms are classified. No bead or frame projecting into either room. The joint between glass and panel sealed with the same cleanroom sealant as the other panel joints, so the whole wall is cleaned with one method.

The sealed cavity also keeps condensation and dust out of the gap between the panes, where no one can reach.

At design review, ask for a section drawing through the vision panel. A ledge that the elevation hides is obvious in section, and it costs far less to remove on paper than after the panels are made.

Cleanroom panels, doors and air handling equipment

Related

More on this subject

The trace matrix gap only a backward read finds

A recovery test with a 20-minute limit, traced to a 15-minute URS requirement, passes and leaves the requirement unproven. Reading a trace matrix from each test back to its requirement finds these weak links and orphan tests. Pick three signed results at random and trace them back.

InsightRead