A split air handling unit leaves the factory with a leakage class and arrives on site as four crates of loose seams.
EN 1886 gives the casing an air leakage class, L1 or L2, measured on a casing that is closed and bolted. A unit too big for the truck ships in sections, and each joint is made on site by whoever holds the spanner that day. The class on the datasheet now depends on that joint.
Walk every joint after the sections are pulled together and before the access panels are closed. The gasket should run in one piece per face, with the corner butt joints glued rather than overlapped; a gasket stretched to fit is thinner where it was pulled. Draw the fixings up in two or three passes, alternating sides of the frame, so the gasket compresses evenly. One loose bolt at a top corner leaves a gap you can slide paper into. Inside, seal the floor seam where the drain pans and floor panels cross the joint, or condensate finds the insulation.
Then run the fans and trace the suction-side seam with smoke. If a section was dropped on a corner in transit, its frame will not sit square against the next one, and the frame gets corrected before anyone starts sealing.
AeroSano units are FAT-tested and witnessed at the factory. The site joint is made after that test, so agree in writing who inspects it and who signs.