The process loads a room data sheet needs before an HVAC price

  • Project Management Consultancy
  • 1 min read

A 5 kW drying oven releasing its heat into a Grade C room needs about 1,500 m³/h of supply air to carry it away.

That is at a 10 K supply temperature difference, and in a small room it can be more air than the grade itself calls for. Then the oven sets the airflow, and with it the size of the unit. The HVAC designer can only do that sum if someone has written the number down.

Room data sheets sent out with a pricing request often stop at grade, area and pressure. To size from, each room also needs a short list per item of equipment:

  1. Heat released into the room in kW, which can be well below the nameplate rating. A water-cooled press or an autoclave with a canopy hood puts much less into the room air than its electrical load suggests.
  2. Which items run at the same time. Two ovens that never run together are one load.
  3. Any air the equipment takes out of the room, since the supply has to replace it.
  4. Moisture released, if any, for the latent side of the coil.

With those blanks empty, each bidder fills them with a guess of their own. The spread between quotes then reflects different assumptions, and the lowest tends to come back as a variation once the real loads are known.

Our AHUs are engineered from the project's own airflow schedule and load calculation, and our design team can help build the room data sheets if they are not done yet.

How our four divisions work together

Related

More on this subject

The trace matrix gap only a backward read finds

A recovery test with a 20-minute limit, traced to a 15-minute URS requirement, passes and leaves the requirement unproven. Reading a trace matrix from each test back to its requirement finds these weak links and orphan tests. Pick three signed results at random and trace them back.

InsightRead