A panel that arrives with a "type-tested" sticker and no routine verification record has proved half of what IEC 61439 asks.
The sticker also dates the paperwork. "Type-tested" and "partially type-tested" are IEC 60439 terms; IEC 61439 replaced them with design verification, and the old standard has been withdrawn for years. Ask which standard and edition the verification was done to.
Design verification, in Clause 10 of IEC 61439-1, proves that a design of assembly works: temperature rise, short-circuit withstand, dielectric properties, clearances, degree of protection and the rest. It is done once for the system, by test, by comparison with a tested reference design, or by assessment where the standard allows.
Every assembly that leaves the workshop then gets routine verification under Clause 11, covering what could go wrong on this particular panel: wiring and connections, terminal torque, protective circuit continuity, degree of protection as built, mechanical operation and a dielectric test. That record should name the design verification it relies on.
At FAT, ask for the design verification report and a routine record tied to the panel serial number, signed by the assembly builder. Our control panels and MCC/MDB are built to IEC 61439 by qualified panel-building partners under our engineering control, and every unit is FAT-tested and witnessed with that record in the equipment file.
Does your panel FAT checklist name both documents?