What happens when one fan in a fan wall stops

  • Manufacturing & Distribution
  • 1 min read

The day one fan in a fan wall stops, its opening becomes a hole in the wall and air runs backwards through it.

N+1 on the datasheet promises the room will not notice. A fan wall is several fans in parallel between two plenums. While they all run, each one holds the pressure difference. A stopped fan holds nothing: the discharge plenum is at higher pressure, so air returns through the idle impeller to the inlet side and goes round again. The running fans now feed the room and the leak.

Whether the room notices depends on what closes that opening. A backdraft damper on each fan does it without a person. A blanking plate needs someone on site with the plate. Dampers cost a little pressure drop every hour of the year, which is the trade.

The remaining fans have to make up the flow as well. With six fans, the five that remain each carry 20% more air at the same pressure and need roughly that much more shaft power. With four fans it is 33%. Motors and drives sized exactly for normal duty cannot give it, and the controller has to be allowed to drive them that far.

One FAT step puts numbers on all of this: run at design duty, switch one fan off at its isolator, and record the airflow, the speed and current of the others, and the time to recover.

Every unit we supply is FAT-tested and witnessed. The single-fan-off step is the one that turns N+1 from a datasheet claim into a reading.

Related

More on this subject

What to check on every BMS graphic

Operators run the plant from BMS graphics, so errors there become operating errors. Check each screen for five things: every value has a unit and a tag, the setpoint sits beside the actual value, alarm colours follow one convention, stale values look different from live ones, and room names match the room codes.

InsightRead

Where a finished cleanroom leaks

For the same excess airflow, room pressure differential varies with the inverse square of the leakage area. On a finished cleanroom that area hides in door gaps, ungasketed light fittings, open socket boxes, panel joints and penetrations. Compare measured excess air with the design allowance at commissioning.

InsightRead