Walk-down before IQ: check the condensate trap

  • Manufacturing & Distribution
  • 1 min read

One check we make on every AHU walk-down before a package goes to qualification: the condensate trap under the cooling coil.

In a draw-through unit the coil section runs under negative pressure, so the drain has to push water out against suction. If the trap's water seal is shallower than the suction it has to hold, air is pulled in through the drain instead. The pan does not empty, and water backs up until it spills into the casing or the next section.

The arithmetic is short. 500 Pa of negative static pressure is about 51 mm of water column, and the seal needs to be deeper than that with margin, plus enough outlet leg for the water to leave. A trap detail copied from a comfort-cooling drawing is often too shallow for a cleanroom unit with high filter pressure drops.

On the walk-down we look at the seal depth against the section pressure on the datasheet, the fall to the drain, and whether the trap can be primed and cleaned. It takes a couple of minutes. A flooded drain pan found during OQ costs a deviation and a retest.

It is one line on the turnover checklist. A package goes to qualification when every such line is closed and recorded, so IQ starts from a verified installation instead of an open punch list.

What is on your walk-down list that never shows up on the drawings?

Related

More on this subject

A retention that pays for the turnover file

Most of a cleanroom HVAC contract is paid before the turnover documents exist. Split the retention into two parts, released on acceptance of the turnover package and of the documents, and size the documentation part on what it would cost the owner to finish as-builts, calibrations and retests without the contractor.

InsightRead

Value engineering after tender: savings that return at OQ

After an over-budget cleanroom HVAC tender, three savings recur: an EN 1886 L2 casing instead of L1, fewer room pressure transmitters, and deleted door drop-seals. Each can reappear as an OQ failure in airflow, alarm testing or pressure differentials, so check every line against its URS requirement and test before accepting it.

InsightRead

WFI belongs in the Contamination Control Strategy

EU GMP Annex 1 (2022) gives WFI circulation above 70 °C as an example of minimizing the risk of microbial growth. Keeping a loop hot drives the design: ASME BPE dead legs of L/D ≤ 2, turbulent flow to the last user point, planned sanitization and sensors on the return. The CCS should justify all of it.

InsightRead