A vendor datasheet arrives marked Rev B, with no revision clouds to show what changed since Rev A.
On a PMC pharma project, noticing that is usually the project administrator's job, along with keeping the revision and status of every drawing and submittal straight until handover.
The main tool is the document register. A typical line holds the document number, revision, date received, reviewer, due date and status. Many projects use a short status scale, for example A for approved, B for approved with comments and C for revise and resubmit; the exact codes come from the project procedure.
Most days are spent checking what arrives against that register. The unclouded Rev B goes back to the vendor, because without clouds a reviewer has to compare two sheets line by line and can miss a changed dimension. When a contractor transmits a drawing at Rev C a week after Rev D was issued, the register is what shows it. And when a submittal returns at status B, someone has to confirm the comments reached the fabricator before cutting starts.
Once a month there is the project report to feed, with schedule, cost and risk inputs to collect, and records to file the way the ISO 9001-aligned quality system sets out.
Humiley has hired project administrators for PMC pharma projects before.
Industries