Technology transfer has no definition of finished until a protocol gives it one.
The first batch at the receiving site can pass while the two sites still disagree on whether the work is done. The acceptance criteria to confirm a successful transfer should be documented a priori in the technology transfer protocol, in the words of WHO's guideline, which also lists what the protocol should include. With your protocol open, look for these:
- Objective and scope are stated, and both units are named with their addresses.
- The transfer team is named, with key personnel from both units and their responsibilities.
- Phases are listed with key activities, deliverables and accountabilities, including the timing of trial and validation batches.
- Acceptance criteria for a successful transfer are written down. "Comparable to the sending site" becomes a criterion only once it says comparable in what, and by how much.
- There is a parallel comparison of premises, equipment, instruments, materials, procedures and methods, with a reference to the gap analysis.
Deviations and sign-off belong to the transfer report, which should record changes, deviations and investigations, be authorised by the responsible person and state whether the transfer was completed.
Without the acceptance criteria, finished means whatever each site remembers agreeing to.