The most moisture-sensitive Li-ion steps run at a −60 °C dew point, about 11 ppm of water vapor, because of what water does in the cell.
The common electrolyte salt, LiPF6, reacts with moisture. One of the products is hydrofluoric acid, which attacks the electrode materials and the surface layers that protect them, and the cell loses capacity over its life. Water that reaches the electrodes or the electrolyte during production is very hard to drive out afterwards, so the protection has to come from the air around the process.
That sets two things for the facility engineer.
First, the drying has to be staged. A cooling coil frosts long before it can dry air this far, so the job is shared:
- Pre-cooling condenses the bulk of the moisture out of the fresh air.
- A desiccant rotor, often two stages for the lowest dew points, adsorbs the rest, with heat driving regeneration.
- Post-cooling removes the heat the rotor adds to the process air.
Second, the specification is written as a dew point at defined locations in the room, with the sensors and acceptance tests to match, because that is the number the chemistry cares about.